Interface says subfloor preparation for its TacTiles connectors is the same as for installations where adhesives would be used.1 CRI 104 describes release adhesive as a thin film of pressure-sensitive adhesive allowed to completely dry, designed for easy removal and replacement.2 Interface does not recommend TacTiles on stairs, ramps, heavy rolling loads or over existing carpet.3
A re-carpet bid where the owner wants to swap tiles later turns on one choice: how the tiles are held down. The Interface and Milliken guides describe three options: adhesive-free connectors, release adhesive in a grid, and release adhesive spread over the whole floor.1 4 Milliken also describes a backing, TractionBack, that is designed to be installed with no adhesive.4
A common assumption is that skipping glue shrinks the prep line. Neither maker says so.1 4 That gap between assumption and instruction is where a bid loses money.

Three ways to hold the tile
Interface says all of its flooring tiles may be secured using TacTiles, its connector squares.3 To replace a tile, the installer lifts it and peels it from the connector.3
Release adhesive is the method CRI 104 describes for carpet tile. Generally, a thin film of pressure-sensitive adhesive is applied and allowed to completely dry.2 CRI 104 says the adhesive is designed to prevent lateral movement and to allow easy removal and replacement.2 Milliken describes its recommended tackifiers the same way. Modules can be removed from the floor and are not permanently adhered.4
In these guides, "full spread" still means release adhesive. Milliken calls for a full spread of adhesive using a short nap paint roller or spray.4 For its standard CQuest backings, Interface allows spray adhesive or free-lay within a 2 meter stabilization grid.1 The grid uses tackifier in a 100 mm band width, allowed to dry fully.1 For its CQuest Bio SONE acoustic backings, Interface says the fixing method should be tackifier release adhesive only, not TacTiles. It adds that an overall application is required when tackifier is used.1
Permanent adhesive shows up mostly on stairs. Milliken requires a permanent contact adhesive for stair risers.4 Interface says tiles on treads, risers and other vertical surfaces must be secured with an approved adhesive.1 For its Interlay underlay, Interface warns that laying tile into its dual-bond adhesive while still wet would create a permanent bond.1 On a swap-ready floor, that outcome defeats the purpose.
| Method | Prep the maker asks for | Limits the maker names |
|---|---|---|
| Connectors (Interface TacTiles) | Same subfloor preparation as installations where adhesives would be used.1 | Not recommended on stairs, ramps, heavy rolling loads or over existing carpet.3 |
| Release adhesive (Milliken) | Smooth and level to within 6mm across 3.5m, hard and dry.4 | Heavy or rolling traffic and ramps may require a stronger tack to prevent lateral movement.4 |
| No adhesive (Milliken TractionBack) | Stringent floor preparation, a thorough mopping, and a flat floor.4 | Under heavy wheeled equipment, Milliken recommends adhering modules with release adhesive.4 |
Prep does not shrink without glue
Interface is explicit. Prep for TacTiles installations is the same as for adhesive installations.1 Its base must be firm, smooth and dry, and all traces of old floor coverings and adhesive residues must be removed.1 Carpet tiles should not be laid over soft surfaces, including existing carpet.1
Milliken sets numbers. Cracks and holes in excess of 3.2mm should be filled with a floor patching material.4 Gypsum based compounds are not recommended.4 Milliken says not to lay coverings until all hygrometer readings show 75% relative humidity or less.4 Interface says humidity on new concrete must not exceed 75% (Hygrometer Test).1
The adhesive-free backing asks for more, not less. Milliken says TractionBack requires stringent floor preparation to be fully functional.4 It calls flatness crucial for TractionBack.4 Moisture and flatness detail by backing type is covered in carpet tile backing systems.
The sources split on who pays for prep. Milliken says all floor preparation is the responsibility of the installer.4 CRI 104 says the owner or general contractor is responsible for providing an acceptable substrate for the specified installation.2 If the bid is silent, the flooring contractor is the one holding the grinder. Price prep as its own line, or exclude it and handle it through a written change order.

Where the connectors go
Interface says to insert tiles based upon the approved installation method and to place TacTiles according to its diagrams.1 The written rules that apply across layouts:
- Lay anchor rows with a TacTiles connector at every joint.1
- Install in all quadrants using a step method, with a connector at every joint.1 Interface's TacTiles sheet shows a second layout, where connectors go as illustrated in the diagram.3
- Place a connector at every joint around the room perimeter and for any cut tiles.3
- TacTiles must also be applied under every cut tile and any tile adjoining the cut tile.1
- Heavy foot traffic may require a higher application rate.1
- Skinny Planks have separate diagrams for ashlar half drop, ashlar variable drop and herringbone.1
Get the diagram for the pattern on the drawings into the submittal. Pattern layouts themselves are covered in carpet tile installation patterns. Mixed backings need a check too. Interface says to ensure the connectors are compatible with each backing, and that Graphlex TacTiles should not come into direct contact with GlasBac backing.3
Getting release adhesive right
Most release adhesive failures come from laying tile too soon. Milliken says the adhesive must be completely dry before modules are installed.4 Its test is simple: press a tile into the adhesive and lift it. There should be no transfer of adhesive to the tile.4 Interface says tackifier should be applied with a roller, never diluted, and allowed to dry completely.1
Raised access floors add a risk. Interface says over-application must be avoided so tackifier does not penetrate between panels and bond them together.1 Milliken calls it good practice to stay 25mm away from panel joints.4 Interface also allows TacTiles or an approved double-sided tape on access floors.1 CRI 104 defers to the manufacturer on roller weight, where rolling is required.2
Old adhesive on a re-carpet: the guides disagree
CRI 104 says old adhesive residue must be removed and encapsulated before new adhesive is applied.2 Interface also requires removal of all adhesive residues.1 Milliken takes a softer line for its own backings. It says the only requirement is to smooth the old adhesive layer until residual trowel notches are less than 1mm.4 Its TractionBack section says an existing pressure-sensitive adhesive film will not interfere, and residual notches should be reduced to 0.8mm or less.4 Milliken also asks installers to pre-test several tiles to confirm they release from the old adhesive.4
That is two figures in one guide. Bid to the tighter one, or get Milliken's answer in writing.
Black adhesive changes the scope. Milliken says never to scrape, sand or mechanically abrade exposed black adhesive, because it may contain asbestos.4 CRI 104 says removal must comply with federal, state and local regulations.2 Exclude abatement from a flooring bid unless it is explicitly priced.

What CRI 104 expects
CRI 104 defers to the carpet manufacturer on tile installation, citing variation in size, shape, backing and method.2 It still sets several baselines:
- A written moisture and alkalinity report from the owner or general contractor before free floating carpet tile systems and glue-down installations.2
- At least two perpendicular chalk lines across the full length and width of the area.2
- Ten tiles measuring 10 times the tile size +/- 1/4 inch, unless the manufacturer states otherwise.2 Milliken's own check uses 11 full modules (10 joints), no more than 3.2mm over the calculated distance.4
- A shop drawing showing installation type, required floor preparation and specified adhesives for each area.2
CRI 104 notes that failure to follow the standard may result in an installation related failure.2 Interface says it cannot accept responsibility for faults caused by installation methods that vary from its guide.1
Swaps after handover
Connectors are not reusable forever. Interface says PVC carpet tiles can normally be removed from a connector twice before the connector needs replacing.3 Bitumen carpet tiles can only be removed once.3 Installers may also cut through the TacTiles joining tiles together.1 Attic stock should therefore include connectors, not just tiles. Matching a replacement tile is covered in replacing a carpet tile.
Maintenance matters on adhesive-free floors. Milliken says edge cuts smaller than half a tile may require spray tackifier if tub vacuum cleaners are used.4 Tell the facility team before the first cleaning crew arrives.
Before you sign the bid
- Name the securing method per area, and attach the maker's placement diagram for the pattern.
- Price prep as a separate line, measured against the maker's numbers, not a general "broom clean."
- State who supplies the moisture and alkalinity report, and get it in writing first.
- Confirm whether old adhesive is removed, encapsulated or smoothed, and which notch limit applies.
- Exclude black adhesive abatement unless priced.
- Flag ramps, stairs and heavy rolling loads; connectors are the wrong tool there.
- Check connector compatibility on every backing in the job.
- Include spare connectors with attic stock, and note how many removals each backing allows.

Sources
- Interface, “Carpet Tile Installation Instructions”. interface.com/content/dam/interfaceinc/interface/technical/emea/installa
- Carpet and Rug Institute, “CRI 104 Standard for Installation of Commercial Carpet”. carpet-rug.org/wp-content/uploads/2019/03/CRI-104-STANDARD-For-INSTALLAT
- Interface, “TacTiles Installation”. specifiedby.com/interface/fotosfera-structured/Interface_Installation_Ta
- Milliken, “Modular Carpet Installation Guidelines”. contenthub.milliken.com/api/public/content/212b9643130e469aa098eefd05147
General information for the flooring trade. This article was drafted with AI assistance and checked against the sources listed above; the manufacturer's current instructions and the project specification govern any real job. If something here is wrong or out of date, tell us.