Walk the floor against the specification and the accepted mockup. The VA master spec, for example, rejects tile installs where more than 5 percent of joints do not touch, requires a 100 pound roller, and bars cuts under 6 inches at walls.1 Check seams, transitions, base and cleaning, then hand over maintenance instructions, product records and extra stock from the same production run.2 3
At the end of a commercial job, the flooring contractor walks the space with the general contractor, the architect or the owner's representative. Everyone carries a list. The items that end up on it are rarely surprises: open joints, a lifted seam, a scuffed area, a gap at a transition, base that is pulling away. Most of them could have been caught a week earlier by the crew, using the same criteria the reviewer will use.
Walk against the specification
A punch walk goes faster when everyone uses the written standard. Specifications often contain concrete acceptance criteria. The Department of Veterans Affairs master specification for resilient tile is a good example. It says more than 5 percent of the joints not touching will not be accepted.1 It requires the floor to be rolled with a minimum 45 kg (100 pound) roller, with no exceptions.1 It says not to provide tile less than 150 mm (6 inches) at walls, and that wall cuts should be of equal width.1 It also says an apparent line of shade or pattern variance will not be accepted.1
Where the specification is silent, the accepted mockup is the standard. A guide specification describes keeping the mockup during construction for workmanship comparison.3 See the mockup checklist.

The usual items, by area
| Area | What to look for |
|---|---|
| Field of the floor | Open or peaked joints, lippage, hollow or loose pieces, adhesive on the surface |
| Seams | Gaps, raised or concave welds, visible seam lines in carpet |
| Perimeter | Small cuts, gaps at walls, edges lifting, base not tight to wall or floor |
| Transitions | Height differences, loose strips, strips off the door centerline |
| Stairs | Movement at the nose, gaps under the nosing, adhesive residue |
| Surface | Scratches, gouges, stains, construction dust in joints |
Look at the floor in more than one light. Paul Pleshek, an inspector writing in Flooring Contractor magazine, recommends photographing the finished floor for overall appearance and in reflected light. He also suggests close-ups of traffic areas, where scratches and gouges may be reported weeks later.4 Do the same during the walk.
Seams and welds
Sheet vinyl seams draw particular attention in healthcare. David Gross of INSTALL describes the target for heat-welded seams: no visible distinction and no raised or recessed area.5 He warns that single-pass skiving leaves concave seams that trap dirt and usually fail visual acceptance.5 For carpet, CRI 104 describes a properly constructed seam as tightly abutted, without gaps or overlaps, with reasonable pattern match.6 It also says a seam will not be invisible.6 That last point helps set expectations at the walk.

Transitions and edges
Transitions are a frequent item because several trades meet there. The VA specification asks for edge strips to be located under the center line of doors unless otherwise shown, set in adhesive or anchored as specified.1 Where the floor edge is exposed, the strip must butt to touch along it.1 For carpet, CRI 104 says the edge of the adjacent flooring should not be more than 1/16” higher than the carpet where no transition molding is used.6 Check every doorway against the shop drawing. See threshold profiles.
Base
Wall base fails in familiar ways: gaps at seams, tops pulling off, loose corners. Most trace to stretching, adhesive coverage or cure time. Roppe asks for base to remain undisturbed for 72 hours after installation.7 Walk it after that window has passed, not on the day it went in. See wall base mistakes.

Cleaning and protection
A floor that looks dirty at the walk gets a long list. The VA specification asks the contractor to follow the manufacturer's instructions for cleaning and protection during construction.1 The guide specification asks for installed product to be protected from damage during construction.3 Clean before the walk with the method the manufacturer allows. Some floors must not be wet-cleaned or finished for a set period. American Floor Mats says not to wash rubber stair treads or apply surface treatments for about one week.8 See floor protection rules.
Fixing the items
Punch repairs should follow the product's own repair method, not a field improvisation. Adhesive on the surface is the simplest. American Floor Mats says adhesive or caulk on stair treads should be wiped off before it dries, using a cloth dampened in denatured alcohol.8 VPI's flash cove instructions ask installers to inspect seams for high spots and excess adhesive, and to clean and repair adhesive spills or seam blowouts.9 For a damaged plank, use the manufacturer's replacement method; see replacing a single plank. For carpet tile, Interface describes lifting the tile from its connector or cutting through the connectors, then setting a new one.10
Take replacements from the job's own stock, not from the cartons meant for the owner, and replace what you use. Note every repair on the list with the date and a photo. If the same item appears twice, find the cause before fixing it a third time.
Closeout documents
A job is not closed until the paperwork is handed over. Texas State University's design standard asks the contractor to include written cleaning and maintenance instructions with closeout documents. It also asks for the manufacturer, type, grade, pattern and color of each tile, with locations where several types are used.2 The guide specification asks for operation and maintenance data for installed products.3 It also asks for extra materials from the same production run as products installed, delivered to the owner in labeled packaging.3 Texas State's standard sets the overage at 5% of each product, or 2% on jobs over 10,000 sf.2
The closeout checklist
- Walk the floor yourself first, against the spec and the mockup.
- Check joints, seams, perimeter, transitions, stairs and surface.
- Walk the base after its cure time.
- Clean by the manufacturer's method; protect until turnover.
- Photograph the finished floor, including in reflected light.
- Hand over maintenance instructions, product records and labeled extra stock.

Sources
- U.S. Department of Veterans Affairs (via WBDG), “Section 09 65 19, Resilient Tile Flooring (master specification)”. nibs-s3-wbdg3-production.s3.us-east-1.amazonaws.com:443/FFC/VA/VANCAS/VA
- Texas State University, “09 65 19 Resilient Tile Flooring and Base design standard”. docs.gato.txst.edu/141401/09_65_19-Resilient-Tile-FlooringBase.pdf
- Regupol America, “Specification Guide, Section 09 65 00 Resilient Flooring (REGUPOL revolution)”. commercial.regupol.com/fileadmin/user_upload/us/products/regupol-revolut
- Flooring Contractor magazine, “Inspector Input (Winter 2019)”. digitaladmin.bnpmedia.com/publication/
- The Construction Specifier, “Inside a perfect seam: the art and science of heat welding vinyl floors”. constructionspecifier.com/inside-a-perfect-seam-the-art-and-science-of-h
- Carpet and Rug Institute, “CRI 104 Standard for Installation of Commercial Carpet”. carpet-rug.org/wp-content/uploads/2019/03/CRI-104-STANDARD-For-INSTALLAT
- Roppe, “Pinnacle Rubber Wall Base Installation”. images.homedepot-static.com/catalog/pdfImages/57/57be32d0-7008-4e29-a273
- American Floor Mats, “How to Install Stair Treads”. americanfloormats.com/content/product/file/document/How%20to%20Install%2
- VPI Corporation, “Flash Cove and Inside/Outside Corner Instructions”. vpicorp.com/downloads/1H%20-%20Instructions-Flash%20Cove%20&%20In-Out%20
- Interface, “Carpet Tile Installation Instructions”. interface.com/content/dam/interfaceinc/interface/technical/emea/installa
General information for the flooring trade. This article was drafted with AI assistance and checked against the sources listed above; the manufacturer's current instructions and the project specification govern any real job. If something here is wrong or out of date, tell us.